When a contractor provides additional construction work not contemplated by the contract is completed at the request of the owner?

Ontario, Canada


The following excerpt is from Jessco Structural Limited v Gottardo Construction Limited, 2016 ONSC 2189 (CanLII):

Taken together, the courts in Ontario have been clear that when additional construction work not contemplated by the contract is completed at the request of the owner, (or in this case the contractor) the party providing the additional work should be paid, as the party requesting the extra work would reasonably expect to pay for it. Requesting this extra work outside the contract is waiver by conduct. The cost for the additional work must be reasonable in the context of the construction project: see Deminico v. Earls, [1945] O.W.N. 375 (H.C.).

Other Questions


If a contractor drafted a contract drafted to be completely unenforceable, when the contractor has not completed the job, can the contract still be enforceable? (Ontario, Canada)
In what circumstances will a construction contractor be required to make progress payments to a contractor during the construction of a project? (Ontario, Canada)
What is the test for interpretation of a commercial contract where the contract states that the contract is not a "contract with respect to the context or factual matrix"? (Ontario, Canada)
What are the factors used to determine whether a party who has not made full disclosure under a contract signed a contract with another party would have signed the contract even if the disclosure had not been made? (Ontario, Canada)
Can an employer in a contract of services claim from the contractor on the ground of breach of contract damages? (Ontario, Canada)
Does the doctrine of contemporaneous exposition apply to a contract where the contract states that the assessment contemplated was the assessment upon which taxes would be imposed in the next year? (Ontario, Canada)
What is the test for a contractor to be entitled to additional payments under a fixed price contract? (Ontario, Canada)
What is the test for a party to a contract where the contract is not binding and the terms of the contract are not binding? (Ontario, Canada)
Does the term owner include the registered owner and the actual owner? (Ontario, Canada)
When an employer unilaterally changes the essential terms of an employee’s contract of employment and the employee does not agree to the changes, is the employee constructively dismissed? (Ontario, Canada)
X



Alexi white


"The most advanced legal research software ever built."

Trusted by top litigators from across North America.